Old Topanga Canyon Road / Mulholland Highway Improvement Project

Print
Share & Bookmark, Press Enter to show all options, press Tab go to next option
GENERAL PROJECT INFORMATION
 Project Title: Old Topanga Canyon Road/ Mulholland Highway Improvement Project
Location: Mulholland Highway from East Old Topanga Road to West Old Topanga, and Old Topanga Canyon Road and Palm Drive
 Project Schedule:
Construction end - Summer 2024
 Contractor: GMZ Engineering, Inc
 Contact: Tatiana Holden, tholden@cityofcalabasas.com

 

 

Mulholland Highway Improvement Project Phase II Draft IS/MND 

Notice of Intent to Adopt a Mitigated Negative Declaration   NEW

Draft Mitigated Negative Declaration Mulholland Highway Safety Improvements Project   NEW

 

 

3 Week Look Ahead Schedule

 

Project Description:

The project consists of improvements on Mulholland Highway from Old Topanga Canyon Road West to Old Topanga Canyon Road East and Old and 200 feet road improvements on Old Topanga Canyon Road West. Improvements include shoulder widening, sidewalks, pavement rehabilitation, storm drain improvements, retaining wall, erosion control, new traffic signal and traffic signal modification, water facility relocation and Wild Walnut Park parking lot improvements.

 

Project Limit Map

 

Project Schedule:

The Mulholland Hwy Improvement Project is currently undergoing two major construction activities.

The major waterline work on Mulholland Hwy initially scheduled for August 30th and September 6th from 9PM to 5AM was successfully completed. The remaining installations are scheduled for September 14th from 9PM to 5AM. The remaining major work is finishing the wall segment near Old Topanga Canyon and Mulholland Hwy east intersection which is pending pole relocation by Southern California Edison in October.

Completion of these two major tasks will allow the contractor, GMZ Engineering Inc., to proceed with repaving of street, and initializing and completing the modification of signals. You can find more details regarding the current work on this project by checking the three-week Look Ahead Schedule.