2024 Street Resurfacing Project

Print
Share & Bookmark, Press Enter to show all options, press Tab go to next option
GENERAL PROJECT INFORMATION
 Project Title: 2024 Street Resurfacing Project
Location: Citywide
Project Schedule: June 2024 – August 2024
Contractor: All American Asphalt
 Contact: Tra’a Bezdecny, tbezdecny@cityofcalabasas.com

 

 

3 Week Look Ahead Schedule

 

Project Description:

The 2024 Street Resurfacing Project includes asphalt cold-milling, asphalt rubberized hot mix (ARHM) overlay, removals and/or reconstruction of pavement sections, median removal, and raised crosswalk install.

 

Streets included:

  • N. Las Virgenes Road (NB 101 exit to Parkmor Road)
  • S. Las Virgenes Road (SB 101 exit to Agoura Road)
  • Park Capri
  • Daisy Trail
  • Clover Trail
  • Locust Drive
  • Canyon Drive (from Clover Trail to Aster Trail)
  • Parkville Road: Installation of Raised Crosswalk between Calamine Drive and Grape Arbor Park entrance

 

Project Update:

July 12, 2024: Paving in Highlands completed

July 5, 2024: Paving of the northern portion of Las Virgenes completed

June 14, 2024: Project begins

June 13, 2024: Proposed median removals on Cold Springs and Lost Springs was removed from this project

June 10-13, 2024:  All American begins mobilization

May 13, 2024: City awarded contract to All American Asphalt

May 7, 2024: Bids received by City

March 22, 2024: Notice inviting sealed bids for the 2024 Resurfacing Project