GENERAL PROJECT INFORMATION | |
Project Title: | Freedom Park |
Location: | Parched Dr. and Balcony Dr. Calabasas, CA 91302 |
Approvals: | City Council approved Capital Improvement Project in June 2023. |
Scope of work: | 1. Replacement of the playground equipment and installation of pour-in-place rubber surfacing 2. Installation of an ADA park entry (bid at a later date) |
Contractor: | Progressive Design Playgrounds dba PDPlay |
Approved Project Budget: | $175,000 (playground equipment) |
Construction Dates: | February - March 2024 |
Contact: | Erica Green egreen@cityofcalabasas.com |
Construction Update – June 28, 2024
Installation of park play equipment and surfacing is complete.
Staff is obtaining bids to construct an accessible entry into the park.
Project Update - 2/29/24