GENERAL
PROJECT INFORMATION |
|
Project Title: |
The Horizons -
Senior Condominiums |
|
Location: |
26705 Malibu
Hills Road (APN: 2064-004-051) (map) |
|
Approvals: |
Planning
Commission: June 22, 2006
Click here to watch video of meeting
File
No(s). CUP 600-004, SPR 006-053, OAK 006-021 & TM6-000-003.
A request for a Conditional Use Permit, Site Plan Review,
Oak Tree Permit and Tentative Tract Map to construct a 60
unit Senior Condominium development and to remove one oak
tree and encroach into the protected zone of another oak
tree, for property located at 26705 Malibu Hills Road (APN:
2064-004-051) within the CB (Commercial-Business Park)
Zoning District.
Submitted by: Steve Kaplan
Planners: Talyn Mirzakhanian & Geoff Starns
City Council: July 19, 2006
Click here to watch video of meeting
Adoption of Resolution No. 2006-1038, requesting a
Conditional Use Permit, Site Plan, and Tentative Tract Map
to construct a 60 unit Senior Condominium development for
property located at 26705 Malibu Hills Road (APN:
2064-004-051) within the CB (Commercial-Business Park)
Zoning District.
Item 7 - Staff Report
A: Resolution No. 2006-1038
B: Planning Commission Resolution No.
06-351
C: Site plans and elevations
D: Color elevation and materials
palette
E: Photographs of the site and
surrounding area
F: Negative Declaration
G: Oak Tree Report
|
|
Construction
Start Date: |
May 2012 |
|
CEQA: |
A Negative
Declaration was adopted for this project. |
|
Contact: |
Talyn Mirzakhanian,
tmirzakhanian@cityofcalabasas.com |
|
On March 15, 2006, an
application was submitted for a Conditional Use Permit, Site Plan
Review, Oak Tree Permit, and Tentative Tract Map to construct a
60-unit senior condominium development, the first in Calabasas,
within the CB (Commercial-Business Park) Zoning District.
The
Spanish Colonial Revival design consisted of a three-story building
over a one level subterranean parking structure, with an adjacent
one-story community building and pool. The site, located at the
eastern terminus of Malibu Hills Road is situated between commercial
and residential properties.
The project was approved by the
Planning Commission in June 2006 and City Council in July 2006.
The project broke ground in May 2012. Completion is anticipated in
Fall 2013. |
|